For those in the construction industry, the right to impose a lien against the improved property in the event of nonpayment is an effective tool to get paid. Chapter 713, Florida Statutes, as well as countless cases require lienors to prepare their liens accurately and to include only lienable items. The failure to properly prepare a claim of lien can result in a claim for punitive damages and exposure to attorney fees and costs.

However, based upon a Fourth District Court of Appeal case, not all is lost if a contractor’s lien is discharged as fraudulent. In fact, despite a contractor’s fraudulent lien, a contractor can still be deemed the prevailing party in an action against an owner and avoid a claim for attorney’s fees.